Aggreko, the provider of mobile and modular power solutions, has signed a contract with Gold Fields, a global mining operator, to provide a total of 25.9 MW hybrid solar and thermal power solutions to the Salares Norte open pit mine in Chile.

This ground-breaking solution has been designed to provide power for the entire mine, which sits at an altitude of 4,500m in the Andes mountain range and is 190km from the nearest town.

diesel gensets and power units 

The hybrid system will comprise both tailor-made high-altitude performance diesel gensets and Aggreko Solar Power units, optimized for off-grid applications and ready to meet the extreme wind conditions these units will experience.

The gensets will each deliver 772 kW and will incorporate Spinning Reserve and Cold Reserve units to efficiently manage peaks in demand. 

reliable, modular power supply

The system will deliver a reliable, modular power supply across all five of the mine’s distribution points

This diesel generation system will be integrated with solar units, which, once installed, will provide 9.9 MW of cost and emission-free power.

The system will deliver a reliable, modular power supply across all five of the mine’s distribution points, whilst surpassing the Chilean government’s environmental standards as well as the Gold Fields’ requirement for a minimum of 20% renewable power generation for mining operations.

energy savings

Once complete, it will achieve $7.4m in cost of energy savings over the next decade and a further $1.1m in carbon tax offset over the Aggreko project lifetime in addition to 104,000 tonnes of carbon emissions savings.

The modular rental solution also supports a consolidated CAPEX outlay, allowing for greater cost control and variable commitments whilst ensuring continued operational excellence at the mine.

clean and efficient power supply

The deployment of this hybrid solution follows Aggreko’s recent launch of Aggreko Solar Power, which will be deployed to provide power at the site.

This market-leading solution is optimized for weak or off-grid energy applications, providing a clean and efficient power supply to a range of operations without long-term financial commitments.

energy transition

Our customers are increasingly looking for more flexible power solutions which can reliably support operations"

Commenting on the news, Pablo Varela, Latin America Managing Director from Aggreko said, “As the energy transition continues to gather pace, our customers are increasingly looking for more flexible power solutions which can reliably support operations whilst reducing carbon emissions and lowering costs."

Pablo Varela adds, "Hybrid products, such as the one we are deploying for Salares Norte, enable a reliable and flexible power supply whilst reducing carbon emissions, thanks to the incorporation of Aggreko Solar Power units as part of the system. Having a standardized product such as this provides the kind of consistency and reliability that our customers have come to expect from us."

power generation

The 10-year contract between Aggreko and Gold Fields for power generation at the mine represents the strong working relationship between the companies and follows a history of successful collaborations globally, such as the recent installation of one of the world’s largest renewable microgrids at Gold Fields’ Granny Smith mine in Western Australia.

At full capacity, Salares Norte will produce an average of 450,000oz of gold per year with Aggreko as the sole power provider.

In case you missed it

Mitsubishi Electric's Call For Energy Reform In UK
Mitsubishi Electric's Call For Energy Reform In UK

Despite 80% of UK homeowners saying they care about climate change, heat pump adoption in UK homes remains critically low, with only 6% making the switch. According to Mitsubishi...

Midea Equipping Contractors To Seize On The Transition To Heat Pumps
Midea Equipping Contractors To Seize On The Transition To Heat Pumps

The HVAC market is in transition. Heat pumps are no longer niche, but are becoming the default replacement for both furnaces and central AC. Midea is responding to the new normal a...

Carrier Corporation Unveils New Coolant Distribution Unit (CDU) For Data Centers
Carrier Corporation Unveils New Coolant Distribution Unit (CDU) For Data Centers

The new Carrier Coolant Distribution Unit, part of the growing QuantumLeap portfolio of purpose-built data center solutions that extends from chip to chiller, is now available. Car...

vfd